Lt Gen Harpal Singh, Director General Border Roads Organization visit the Atal Tunnel to review the construction work on Manali-Leh road.
Atal Tunnel, world's longest highway tunnel connecting Manali with Leh is ready
1 min read . 16 Sep 2020
ANI
The construction of the Atal Tunnel connecting Manali with Leh has been completed in a span of 10 years
Atal Tunnel is the world's longest highway tunnel above 10,000 feet
Manali: The construction of the Atal Tunnel connecting Manali with Leh, which is the world's longest highway tunnel above 10,000 feet, has been completed in a span of 10 years whereas the original estimated time was less than six years.
"Atal Tunnel, connecting Manali to Leh, is the world's longest highway tunnel above 10,000 feet. The estimated period for completion of this tunnel was less than 6 years but it was completed in 10 years," said KP Purushothaman, Chief Engineer.
"There are CCTV cameras at every 60 metres and emergency exit tunnels at every 500 metres inside the tunnel. The tunnel will reduce the distance between Manali and Leh by 46 kilometres and four hours can be saved," said Purushothaman.
Fire hydrants have also been installed inside the tunnel in case of any fire incident.
"The induction and de-induction of resources was a difficult task while it was under construction. We did face a lot of challenges but together we were able to complete its construction. The tunnel's width is 10.5 metres, including footpath of 1 metre on both sides," said Purushothaman.
Speaking to ANI, Colonel Parikshit Mehra, Director, Atal Tunnel project said that many experts working within the team were of the opinion to change the alignment of the tunnel.
"We have had this dream to connect Leh and this was the first step to the connectivity ladder. This tunnel was a challenging project because we were working only from two ends. The other end was in North, across the Rohtang Pas which was accessible only for around five months in a year," he added.
This story has been published from a wire agency feed without modifications to the text. Only the headline has been changed
Lt Gen Harpal Singh, Director General Border Roads Organization visit the Atal Tunnel to review the construction work on Manali-Leh road. Atal Tunnel, world's longest highway tunnel connecting Manali with Leh is ready 1 min read . 16 Sep 2020 ANI The construction of the Atal Tunnel connecting Manali with Leh has been completed in a span of 10 years Atal Tunnel is the world's longest highway tunnel above 10,000 feet
Manali: The construction of the Atal Tunnel connecting Manali with Leh, which is the world's longest highway tunnel above 10,000 feet, has been completed in a span of 10 years whereas the original estimated time was less than six years.
"Atal Tunnel, connecting Manali to Leh, is the world's longest highway tunnel above 10,000 feet. The estimated period for completion of this tunnel was less than 6 years but it was completed in 10 years," said KP Purushothaman, Chief Engineer.
"There are CCTV cameras at every 60 metres and emergency exit tunnels at every 500 metres inside the tunnel. The tunnel will reduce the distance between Manali and Leh by 46 kilometres and four hours can be saved," said Purushothaman.
Fire hydrants have also been installed inside the tunnel in case of any fire incident.
"The induction and de-induction of resources was a difficult task while it was under construction. We did face a lot of challenges but together we were able to complete its construction. The tunnel's width is 10.5 metres, including footpath of 1 metre on both sides," said Purushothaman.
Speaking to ANI, Colonel Parikshit Mehra, Director, Atal Tunnel project said that many experts working within the team were of the opinion to change the alignment of the tunnel.
"We have had this dream to connect Leh and this was the first step to the connectivity ladder. This tunnel was a challenging project because we were working only from two ends. The other end was in North, across the Rohtang Pas which was accessible only for around five months in a year," he added.
This story has been published from a wire agency feed without modifications to the text. Only the headline has been changed