Today we had a long meeting for progress of the whole year projects:
• 87 Qualifications remaining :
• On time execution + analysis & anticipation/ back-up plan -> missed out items lessons learnt (qual task, scopes, semitool link missed out etc ..)
• G4 closure:
• PR event link / flexibility follow up
• Rack ID change on time
• Staffing model & training anticipation
• 6 Tools shutdown on time
• Line audit
• Shutdown or decontamination checklist
• On time execution
• Resources allocation to the HYT consolidation Project after organization merge.
• Daily PCRB
• SWR turn at 10.5 : Module Project owner & Production : To focus & escalate
• T4 closure delay (min 1 week) -> (Alloy -> LTO)– Midas Detector Quote/PRPO/Installation late. SWR done.– (Lack of Focus).
• GDSTRE01 (Paddle SD-> Nzone)/ (Lydop) / (Pzone) – Gain higher than std. Device requested to continue with EWS results. – (additional iPCRB request)
• 88B2 (Boron ->Pzone): JU7 re-trial (2 wafers) pending WIT1, with retrial of U87 sample and full run, (Technical issues)
• CHC2 (Oxidation -> Pzone) : To follow the qualification similar to 765B2. 2 wafers to send as trial & 9 trial wafer to send for SRP testing > (additional iPCRB request)
• 5URA1 (SD-> Nzone): WIT1 OBSERVED ISSUE . PENDING WIT2. Device request for EWS instead of wit2 (as gain seen higher for swr lots) – (additional iPCRB request)
• 4YS3 : To start qualification in W52/W01 for Pgm 15 thin oxide measurement – (Lack of Focus / Change priorities)
• JDUY4 (Poly-> NiTi) : STACK MEMORY FULL (NEED TO REMOVE SOME OBSELETE RECIPES FIRST) - NI SINTERING, NITI SINTERING SINCE ONLY W03 INPUT NITI (Lack of Focus / Change priorities)
• UYP07 (PiUYha) : Delay in initial hookup of auto-fill due to PRPO > concurrently delay in release for 4IOP07 conversion. (Lack of Focus)
• 1YTE1 (Nanospec backup): Focus on the above tube qualifications > (Change priorities)