I got to the site safely. The sun is now at its peak as you can see in the first photo and I am starting to have sun burns. Welding works has commenced for the galvanized steel pipes we’d be using as columns for the animal house. Block production is also on going. We’d be using over 20,000 sandcrete blocks to develop the site so we figured that I’d be cheaper to produce them onsite as this will save cost of transporting them to the site if we had chosen to by offsite. Today seems like a productive day. I just wish the intensity of the sun will go down. How is it going over there? #Photography
2 comments
The blocks, are they hand moulded or with machine? Because cost of renting a machine and having it on site for days is now much. Though 20k is huge, it might be worth it and even cheaper than buying.
Over 20,000 blocks , that's a lot, what building are you guys building and what role do you partake